File 219 · 2008 · Barcelona

Ícaro

Restaurant

procedures
4
authority
1
years
2

The commission

  • Activity project
  • Building project
  • Site supervision
  • Technical certificate
  • Low-voltage electrical installation

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2008 Barcelona City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

  2. 2
    2008 Barcelona City Council

    Technical project

    What it is. Document drawn up and signed by the engineer describing and justifying the premises, activity, works or installations and showing that they comply with the rules. It is the technical basis of most procedures.

  3. 3
    2009 Barcelona City Council

    Technical certificate of the activity

    What it is. Document signed by the engineer certifying that the premises and their installations have been built as designed and comply with the applicable rules. It is submitted to the City Council in order to open.

  4. 4
    2009 Barcelona City Council

    Certificate of completion of works

    What it is. Document in which the supervising engineer confirms that the works have been completed in line with the project or the documents submitted. It is handed to the City Council on completion.