File 862 · 2020 · Castelldefels

Panchito

Mexican restaurant in a shopping centre: works, activity and supply

procedures
6
authorities
4
year
1

The commission

The contractor commissioned us to do the first restaurant of this Mexican chain, in a shell unit with a terrace inside a shopping centre. We submitted the notification of works a few days before the lockdown and resumed the work when the site restarted.

We used the shopping centre's conditions to simplify the project, integrating the unit into the building's safety arrangements and shared services. We took on the technical management, legalised the electrical installation, arranged the new supply and submitted the notification of opening.

  • Building project
  • Site supervision
  • Prior notification
  • Activity project
  • Technical certificate
  • Low-voltage electrical installation
  • Drawings

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2020 Castelldefels City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We wrote the works project and submitted the notification, and then took on the technical management.

  2. 2
    2020 Distribution company

    New electricity supply

    What it is. Request to the distribution company for a new electricity supply point, including a temporary supply for building works. The company sets the technical and financial terms for connecting to its grid.

    What we did. We arranged with the distribution company the application for the new electricity supply.

  3. 3
    2020 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We defined the electrical installation, coordinated the installer and accompanied the initial inspection.

  4. 4
    2020 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

    What we did. We prepared the documents and processed the registration of the electrical installation with the Government of Catalonia.

  5. 5
    2020 Castelldefels City Council

    Certificate of completion of works

    What it is. Document in which the supervising engineer confirms that the works have been completed in line with the project or the documents submitted. It is handed to the City Council on completion.

    What we did. We issued the certificate of completion of the works as the supervising engineer and submitted it to the City Council.

  6. 6
    2020 Castelldefels City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We wrote the activity project and submitted the notification of opening with the technical certificate.

The finished premises

Suspended ceiling with light fittings and ventilation grilles in the kitchen area
Suspended ceiling with light fittings and ventilation grilles in the kitchen area