File 582 · 2015–2016 · Barcelona

Yatai

Japanese restaurant with open kitchen: works, activity and opening

procedures
6
authorities
4
years
2

The commission

A couple of restaurateurs wanted to open their second Japanese restaurant, with part of the cooking in view of the public. The unit had been closed for some time: we made use of the previous activity's documents and obtained a new planning report. As the building is listed, we processed the works with a heritage report.

We designed the cooking area with them and resolved the installations by making use of what was already there, which simplified the licensing. The delicate point was coexisting with the neighbours: we carried out our own checks before the approved collaborating body's check, which was favourable, and submitted the notification of opening.

  • Activity project
  • Prior notification
  • Technical certificate
  • Building project
  • Site supervision
  • Low-voltage electrical installation
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2015 Barcelona City Council Passed

    Planning report

    What it is. Report by the City Council stating whether a use or activity is compatible with the planning rules at a specific location. It is best requested before committing to the premises or submitting the project.

    What we did. We applied for the planning report on the compatibility of the activity and renewed it to keep it valid.

  2. 2
    2015 Heritage service Passed

    Heritage report

    What it is. Report by the heritage service on works or signs in buildings or features protected for their historical or architectural value. It sets the conditions so that the work respects the protected asset.

    What we did. We processed the prior heritage report for the works and adapted the project to its conditions.

  3. 3
    2015 Association of Industrial Engineers Passed

    Technical suitability report

    What it is. Report by an approved collaborating body that reviews the project or the works and certifies that they meet planning and technical rules. Some councils, such as Barcelona, accept it to speed up the process.

    What we did. We wrote the works project and submitted it to obtain the technical suitability report.

  4. 4
    2015 Barcelona City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We submitted the notification of the works with the technical project and managed their execution.

  5. 5
    2016 Approved collaborating body

    Technical certification by an approved inspection body

    What it is. Review of the project and the finished works by a collaborating body accredited by the authorities, which certifies to the City Council that the activity complies with the rules. Some municipalities require it to open.

    What we did. We wrote the activity project and coordinated the approved collaborating body's review, visits and measurements.

  6. 6
    2016 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We submitted the notification of opening with the technical certification.

The finished premises

Accessible toilet with a pedestal-free washbasin and grab rail
Accessible toilet with a pedestal-free washbasin and grab rail