File 847 · 2019–2020 · Castelldefels

Timesburg

Burger restaurant in a shopping centre: works, activity and low voltage

procedures
6
authorities
4
years
2

The commission

The chain was opening a new restaurant on a newly refurbished floor of a shopping centre, in a unit occupied for the first time. We agreed the design with the brand, the interior designer and the centre's technical management, and validated the criteria with the municipal technical services before submitting the works.

We integrated the restaurant's services with those of the building and took on the technical management of the works. We legalised the low voltage just before the planned opening, which the 2020 lockdown postponed. We then completed the final documents and submitted the notification of opening.

  • Building project
  • Site supervision
  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Fire protection
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2019 Castelldefels City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We wrote the works project, submitted the prior notification and issued the certificate of completion of works.

  2. 2
    2020 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We prepared the electrical installation and arranged the initial inspection with the inspection body.

  3. 3
    2020 Castelldefels City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We wrote the activity project and the technical certificate and submitted the prior notification of opening.

  4. 4
    2020 Government of Catalonia

    Registration of the fire-protection installation

    What it is. Registration with the Government of Catalonia of fire-protection installations, such as extinguishers, fire hose reels or automatic detection or suppression systems, with the installer's certificate (RIPCI).

    What we did. We prepared the documents for the fire-protection installation and processed its registration.

  5. 5
    2020 Government of Catalonia

    Registration of the thermal installation

    What it is. Registration with the Government of Catalonia of heating, air-conditioning or hot water installations that require it because of their power, with the installer's certificate and, where required, the design (RITE).

    What we did. We coordinated with the installer the documents for the thermal installation and its registration.

  6. 6
    2020 Distribution company

    Power upgrade with the distribution company

    What it is. Request to the distribution company to increase the electrical power available to a supply. It may involve work on the service connection and payment of extension and access charges.

    What we did. We calculated the electrical needs and arranged the power upgrade with the distribution company.

The finished premises

Stainless-steel kitchen with extraction hood
Stainless-steel kitchen with extraction hood
Extraction fan box and flue on the shopping centre roof
Extraction fan box and flue on the shopping centre roof

Nearby