File 660 · 2016–2018 · Castelldefels

Happy Castell

Restaurant bar with children's play area

procedures
6
authorities
4
years
2

The commission

The client wanted to join a former restaurant and the garage next door into a single venue: a restaurant bar in one part and a large children's play area in the other. We designed the layout with them to make the most of both spaces, with the families' experience in mind: parents can eat in peace while keeping an eye on the children playing.

Based on their requirements we designed the refurbishment and the installations, submitted the prior notification of works with a project and managed the works. We legalised the electrical installation, with a favourable initial inspection, and submitted the prior notification of opening with the activity project.

  • Building project
  • Site supervision
  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Building service connection
  • Drawings

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2016 Castelldefels City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We wrote the works project and submitted the prior notification of the works.

  2. 2
    2017 Distribution company

    Power upgrade with the distribution company

    What it is. Request to the distribution company to increase the electrical power available to a supply. It may involve work on the service connection and payment of extension and access charges.

    What we did. We calculated the electrical needs and arranged the power upgrade with the distribution company.

  3. 3
    2017 Inspection body

    Sound insulation test

    What it is. On-site test by an accredited body measuring the sound insulation, or the noise reaching neighbouring homes, and checking that it meets the limits of the local by-law and Catalan Law 16/2002.

    What we did. We coordinated with the accredited body the sound insulation test of the premises.

  4. 4
    2017 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We prepared the electrical installation and arranged the initial inspection with the inspection body.

  5. 5
    2017 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

    What we did. We prepared the electrical installation documents and processed its registration.

  6. 6
    2017 Castelldefels City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We wrote the activity project and the technical certificate and submitted the prior notification of opening.

The finished premises

Restaurant dining room with suspended ceiling and long tables
Restaurant dining room with suspended ceiling and long tables
Colourful tables and benches for children
Colourful tables and benches for children
Kitchen extraction hood and duct
Kitchen extraction hood and duct