File 735 · 2018 · Sant Cugat del Vallès

Timesburg

Burger restaurant on a historic square: works, activity and terrace

procedures
6
authorities
4
year
1

The commission

The burger chain wanted to set up in a former estate agency's office on one of the most central and historic squares in the city, within a listed area. We studied the viability of the premises with the municipal office before committing the investment and processed the power upgrade with the distribution company.

We wrote the works project and managed the refurbishment, taking care of the dwelling above and of the listed surroundings.

We legalised the electrical installation and submitted the prior notification of the activity, the terrace application and the health notification.

  • Feasibility study
  • Technical report
  • Building project
  • Site supervision
  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Terrace licence

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2018 Distribution company

    Power upgrade with the distribution company

    What it is. Request to the distribution company to increase the electrical power available to a supply. It may involve work on the service connection and payment of extension and access charges.

    What we did. We applied to the distribution company for the power upgrade and handled its conditions.

  2. 2
    2018 Sant Cugat del Vallès City Council

    Minor works licence

    What it is. Municipal permit for small-scale works which, because of their nature or the local by-law, cannot be carried out with a simple notification. It is obtained before starting, with the technical documents.

    What we did. We wrote the works project, processed the minor works licence and managed the execution.

  3. 3
    2018 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We prepared the electrical installation documents and coordinated the initial inspection.

  4. 4
    2018 Sant Cugat del Vallès City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We checked planning compatibility, wrote the activity project and submitted the prior notification.

  5. 5
    2018 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

    What we did. We processed the registration of the electrical installation with the inspection report.

  6. 6
    2018 Sant Cugat del Vallès City Council

    Responsible declaration on health requirements

    What it is. Statement by the holder to the health authority that the premises, such as a food shop or a beauty centre, meet the hygiene and health safety requirements for their activity.

    What we did. We prepared the documents and submitted the notification of opening and the responsible declaration for the food sector.

The finished premises

Steel joists and beams during the refurbishment
Steel joists and beams during the refurbishment