File 342 · 2011–2012 · Barcelona

KFC

Fast-food restaurant: licence, works and opening

procedures
6
authorities
3
years
2

The commission

An international fast-food chain occupied a unit that had already been a restaurant. We worked alongside the architecture practice designing the refurbishment and took care of the technical side and the applications: the transfer of the previous licence, the works and the power upgrade, as well as the activity project and the final certificate.

We planned the power upgrade so as not to have to wait for changes to the network, and resolved the safety requirements of the premises so that they complied without complications. We coordinated the approved collaborating body's check until all the closing documents were gathered and submitted the notification of opening with technical certification.

  • Activity project
  • Change of licence holder
  • Prior notification
  • Technical certificate
  • Building service connection

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2011 Barcelona City Council

    Change of activity holder

    What it is. Procedure to transfer an already authorised activity to a new holder, for example when a business changes hands. The new holder takes on the conditions of the existing licence or notification.

    What we did. We prepared the technical documents and processed the change of holder of the previous activity's licence.

  2. 2
    2011 Barcelona City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We wrote the documents for the interior refurbishment works and submitted the notification.

  3. 3
    2011 Barcelona City Council

    Minor works licence

    What it is. Municipal permit for small-scale works which, because of their nature or the local by-law, cannot be carried out with a simple notification. It is obtained before starting, with the technical documents.

    What we did. We wrote the technical documents for the works and processed the licence.

  4. 4
    2011 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We prepared the electrical installation and arranged the initial inspection with the inspection body.

  5. 5
    2011 Government of Catalonia

    Registration of the thermal installation

    What it is. Registration with the Government of Catalonia of heating, air-conditioning or hot water installations that require it because of their power, with the installer's certificate and, where required, the design (RITE).

    What we did. We prepared the thermal installation certificate and processed its registration.

  6. 6
    2012 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We wrote the activity project and the technical certificate, coordinated the approved collaborating body's certification and submitted the notification of opening.