aten proyectos
Projects

File 861 · 2020 · Barcelona

Food retail

procedures
4
authorities
3
year
1

The commission

  • Building project

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2020 Barcelona City Council

    Preliminary enquiry

    What it is. Formal enquiry to the City Council, before starting a procedure, about whether an activity or works are feasible in specific premises or which documents will be needed.

  2. 2
    2020 Approved collaborating body Passed

    Technical suitability report

    What it is. Report by an approved collaborating body that reviews the project or the works and certifies that they meet planning and technical rules. Some councils, such as Barcelona, accept it to speed up the process.

  3. 3
    2020 Barcelona City Council Accepted

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

  4. 4
    2020 Heritage service Passed

    Heritage report

    What it is. Report by the heritage service on works or signs in buildings or features protected for their historical or architectural value. It sets the conditions so that the work respects the protected asset.