File 682 · 2017 · Barcelona

Neko

Restaurant

procedures
5
authorities
4
year
1

The commission

  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Terrace licence
  • Drawings

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2017 Barcelona City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

  2. 2
    2017 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

  3. 3
    2017 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

  4. 4
    2017 Approved collaborating body Passed

    Technical certification by an approved inspection body

    What it is. Review of the project and the finished works by a collaborating body accredited by the authorities, which certifies to the City Council that the activity complies with the rules. Some municipalities require it to open.

  5. 5
    2017 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.