File 1111 · 2024 · Molins de Rei

Solar PV installation

procedures
3
authorities
2
year
1

The commission

  • Solar PV installation
  • Building project
  • Technical certificate
  • Low-voltage electrical installation

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2024 Distribution company

    Grid access and connection with the distribution company

    What it is. Permits from the distribution company to connect a generating installation, such as a solar PV system, or a sizeable load to its grid. They confirm grid capacity and set the connection point.

  2. 2
    2024 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

  3. 3
    2024 Government of Catalonia

    Operating authorisation

    What it is. Decision by the Government of Catalonia allowing a completed electricity generating installation to start operating, together with its final entry in the production or self-consumption register.