File 1083 · 2023 · Begur

Solar PV installation

procedures
4
authorities
3
years
2

The commission

  • Solar PV installation
  • Building project
  • Technical certificate
  • Low-voltage electrical installation
  • Other work

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2023 Begur City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

  2. 2
    2023 Government of Catalonia

    Legalisation of the self-consumption installation

    What it is. Registration with the Government of Catalonia of a solar PV or other low-voltage generating installation, with its certificate and, where required, the design, as a step before commissioning it.

  3. 3
    2024 Distribution company

    Grid access and connection with the distribution company

    What it is. Permits from the distribution company to connect a generating installation, such as a solar PV system, or a sizeable load to its grid. They confirm grid capacity and set the connection point.

  4. 4
    2024 Government of Catalonia

    Operating authorisation

    What it is. Decision by the Government of Catalonia allowing a completed electricity generating installation to start operating, together with its final entry in the production or self-consumption register.