File 1184 · 2024 · Alcanar | La Pobla de Segur

Solar PV installation

procedures
3
authorities
3
years
2

The commission

  • Solar PV installation
  • Building service connection
  • Low-voltage electrical installation

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2024 Alcanar City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

  2. 2
    2025 Distribution company

    Grid access and connection with the distribution company

    What it is. Permits from the distribution company to connect a generating installation, such as a solar PV system, or a sizeable load to its grid. They confirm grid capacity and set the connection point.

  3. 3
    2025 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.