aten proyectos
Weights machines and cardio bikes in the warehouse
Projects

File 1115 · 2024–2025 · Mollet del Vallès

Eleven Private Sport Club

Gym in a former commercial unit

procedures
6
authorities
4
years
2

The commission

The client wanted to convert a unit that had been a car dealership and a supermarket into a full gym. Based on their requirements we designed the layout with them to make the most of the space and with members' comfort in mind, with training areas, a café and changing rooms.

Together with the client we made the preliminary enquiry to the City Council, the fire-protection project with a favourable prior report and the endorsed execution project with which we obtained the change-of-use licence, including the roads authority's report.

We then managed the works, legalised the installations with favourable inspections and processed the first occupation with the acoustic test. Finally we submitted the notification of start of activity with project and certificate, together with the café's health declaration, so that the client could start with everything in order.

  • Building project
  • Site supervision
  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Fire protection
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2024 Catalan Fire and Rescue Service Passed

    Fire-prevention report

    What it is. Report by the fire service on the fire-prevention measures of a project, such as evacuation or fire resistance. Some activities require it because of their size or risk (Catalan Law 3/2010).

    What we did. We wrote the fire-protection project and processed the prior report.

  2. 2
    2025 Mollet del Vallès City Council Granted

    Planning permission for use

    What it is. Planning permission to put a building, premises or plot to a different use, or to a use that needs specific approval, such as an activity on land not designated for development.

    What we did. We wrote the endorsed execution project and processed the planning licence for the change of use, with the roads authority's report.

  3. 3
    2025 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We prepared the electrical installation and arranged the initial inspection with the inspection body.

  4. 4
    2025 Government of Catalonia

    Registration of the fire-protection installation

    What it is. Registration with the Government of Catalonia of fire-protection installations, such as extinguishers, fire hose reels or automatic detection or suppression systems, with the installer's certificate (RIPCI).

    What we did. We gathered the certificates for the fire-protection installation and processed its registration.

  5. 5
    2025 Catalan Fire and Rescue Service Passed

    Fire-prevention compliance check

    What it is. Inspection visit after the works are finished, in which the fire service or an approved collaborating body checks that fire-prevention measures match the reviewed project (Catalan Law 3/2010).

    What we did. We arranged the compliance visit with the approved collaborating body and submitted the favourable certificate.

  6. 6
    2025 Mollet del Vallès City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We submitted the notification of start of activity with the technical project and the certificate, together with the health declaration.

The finished premises

Painted warehouse façade facing a square
Painted warehouse façade facing a square
Café area with a long table and benches on artificial grass
Café area with a long table and benches on artificial grass
Ventilation duct above the training area, under the warehouse roof
Ventilation duct above the training area, under the warehouse roof

Nearby

Similar projects