File 1143 · 2024–2025 · Terrassa

Escola Bressol Eina

Nursery school: updating the safety conditions

procedures
5
authorities
3
years
2

The commission

Together with the client we updated the safety conditions of this nursery school, with the children and the staff who use it every day in mind. We handled both the technical side and the paperwork.

The work covered updating the electrical installation, with a favourable initial inspection; surveying new drawings; a statement justifying compliance with the safety and accessibility requirements; and the project and site management for the works that improved the separation between the building's garage and the entrance to the school.

  • Technical report
  • Technical certificate
  • Low-voltage electrical installation
  • Drawings
  • Building project
  • Site supervision

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2024 Terrassa City Council

    Municipal check of the activity

    What it is. Review by the City Council, on paper or through a visit to the premises, which checks that the activity matches what was submitted and the by-laws, including noise rules, and records the outcome.

    What we did. We prepared the activity report with the updated drawings and the justification of the non-substantial changes.

  2. 2
    2024 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We defined the update of the electrical installation, coordinated the installer and accompanied the initial inspection.

  3. 3
    2024 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

    What we did. We prepared the electrical installation documents and processed its registration.

  4. 4
    2024 Terrassa City Council

    Change of activity holder

    What it is. Procedure to transfer an already authorised activity to a new holder, for example when a business changes hands. The new holder takes on the conditions of the existing licence or notification.

    What we did. We wrote the activity's technical certificate and justified the electrical legalisation for the change of name on the licence.

  5. 5
    2025 Terrassa City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We wrote the technical documents for the works and submitted the prior notification.

The finished premises

Bright classroom with shelves, a toy kitchen and a ceiling fan
Bright classroom with shelves, a toy kitchen and a ceiling fan
Finished protected lobby with the new fire door
Finished protected lobby with the new fire door
New distribution board with labelled circuits
New distribution board with labelled circuits