File 823 · 2019 · Montgat

Englishpitinglis

Educational centre

procedures
4
authorities
3
year
1

The commission

  • Responsible declaration
  • Technical certificate
  • Building project
  • Low-voltage electrical installation
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2019 Montgat City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

  2. 2
    2019 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

  3. 3
    2019 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

  4. 4
    2019 Montgat City Council

    Responsible declaration of opening

    What it is. Statement by the holder, on their own responsibility, that the premises meet all requirements for the activity. The business may open once it is filed, and the council checks it afterwards (Catalan Law 18/2020).