File 628 · 2016 · Mollet del Vallès

Parking Jaume I

Surface car park: activity and electrical installation

procedures
4
authorities
2
years
2

The commission

The owner of a plot had just built an automated open-air public car park and needed to legalise the activity and the electrical installation. We designed the installation together with the contractor. Given its characteristics, it needed neither a project nor an initial inspection by an inspection body, which saved the client time and cost.

We visited the site, met the municipal technical staff to agree the procedure and wrote the activity project and the final certificate. We registered the low-voltage installation and prepared the responsible declaration of opening, the regime that applies to this activity.

  • Activity project
  • Prior notification
  • Responsible declaration
  • Technical certificate
  • Low-voltage electrical installation
  • Drawings

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2015 Mollet del Vallès City Council Granted

    Temporary use licence

    What it is. Municipal permit for a temporary use or temporary works until the planned development goes ahead. The City Council may revoke it when needed, without compensation.

    What we did. We prepared the technical documents and processed the temporary uses and works licence for building the car park.

  2. 2
    2016 Mollet del Vallès City Council Granted

    Major works licence

    What it is. Municipal permit for major works, such as those affecting the structure, changing the use or layout of the building or demolishing a construction. It requires a technical project and is obtained before starting.

    What we did. We prepared the technical documents and processed the demolition licence for the plot.

  3. 3
    2016 Mollet del Vallès City Council

    Responsible declaration of opening

    What it is. Statement by the holder, on their own responsibility, that the premises meet all requirements for the activity. The business may open once it is filed, and the council checks it afterwards (Catalan Law 18/2020).

    What we did. We wrote the activity project and the final certificate and submitted the responsible declaration of opening.

  4. 4
    2016 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

    What we did. We designed the electrical installation, prepared the certificate and processed its registration.

The finished premises

Accessible spaces beside the entrance and the control kiosk
Accessible spaces beside the entrance and the control kiosk
Car park electrical switchboard during installation
Car park electrical switchboard during installation

Nearby