aten proyectos
Sales floor with illuminated trainer displays and a cast-iron column
Projects

File 614 · 2015–2016 · Barcelona

Sivasdescalzo

Trainers shop in a listed building: works, activity and low voltage

procedures
6
authorities
4
year
1

The commission

The brand was opening a shop in a listed building and wanted to leave its original structure exposed. We wrote the works project, the activity project and the electrical project, and processed the works with a heritage report.

We resolved the safety requirements while respecting the character of the building, with the execution checked by a laboratory, and coordinated the structural calculations the refurbishment needed. The approved collaborating body reviewed the project, carried out the check and certified the activity. We gathered the documents for all the installations and submitted the notification of opening.

  • Building project
  • Site supervision
  • Activity project
  • Technical certificate
  • Low-voltage electrical installation

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2016 Barcelona City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We wrote the works project and submitted the notification of the works.

  2. 2
    2016 Approved collaborating body Passed

    Technical suitability report

    What it is. Report by an approved collaborating body that reviews the project or the works and certifies that they meet planning and technical rules. Some councils, such as Barcelona, accept it to speed up the process.

    What we did. We prepared the project documents and submitted them to the approved collaborating body to obtain its suitability report.

  3. 3
    2016 Heritage service Passed

    Heritage report

    What it is. Report by the heritage service on works or signs in buildings or features protected for their historical or architectural value. It sets the conditions so that the work respects the protected asset.

    What we did. We prepared the documents for the intervention and the signs and processed the prior heritage report.

  4. 4
    2016 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We wrote the electrical project and arranged the initial inspection with the inspection body.

  5. 5
    2016 Approved collaborating body Accepted

    Technical certification by an approved inspection body

    What it is. Review of the project and the finished works by a collaborating body accredited by the authorities, which certifies to the City Council that the activity complies with the rules. Some municipalities require it to open.

    What we did. We dealt with the approved collaborating body's project review, check and acoustic measurement until it issued its certification.

  6. 6
    2016 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We gathered the documents for all the installations and submitted the notification of opening of the activity.

The finished premises

Stairs to the basement beside the brick wall, with an exit sign
Stairs to the basement beside the brick wall, with an exit sign