File 1045 · 2023 · Barcelona

Van Cleef & Arpels

Retail

procedures
4
authorities
2
year
1

The commission

  • Low-voltage electrical installation
  • Fire protection
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2023 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

  2. 2
    2023 Government of Catalonia

    Registration of the thermal installation

    What it is. Registration with the Government of Catalonia of heating, air-conditioning or hot water installations that require it because of their power, with the installer's certificate and, where required, the design (RITE).

  3. 3
    2023 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

  4. 4
    2023 Government of Catalonia

    Registration of the fire-protection installation

    What it is. Registration with the Government of Catalonia of fire-protection installations, such as extinguishers, fire hose reels or automatic detection or suppression systems, with the installer's certificate (RIPCI).