aten proyectos
Open-plan office floor with sprayed acoustic ceiling and exposed columns
Projects

File 984 · 2022 · Barcelona

Fundació FC Barcelona

Management offices of the FC Barcelona Foundation: works, low voltage and opening

procedures
5
authorities
4
year
1

The commission

We accompanied the contractor in the design-and-build tender for the new management offices of the FC Barcelona Foundation, on an office floor very close to the Camp Nou. From the tender stage we advised on the critical points of the premises.

With the works awarded, we wrote the minor works project and obtained the approved collaborating body's favourable technical suitability report. We resolved the safety requirements of the premises.

We took on the technical management, designed the electrical installation, passed the initial inspection and submitted the notification of opening and the registration of the installation.

  • Building project
  • Site supervision
  • Low-voltage electrical installation
  • Prior notification
  • Drawings
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2022 Barcelona City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

    What we did. We wrote the works project and submitted the immediate notification of the works.

  2. 2
    2022 Approved collaborating body Passed

    Technical suitability report

    What it is. Report by an approved collaborating body that reviews the project or the works and certifies that they meet planning and technical rules. Some councils, such as Barcelona, accept it to speed up the process.

    What we did. We prepared the project documents and submitted them to obtain the technical suitability report.

  3. 3
    2022 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

    What we did. We prepared the electrical installation and arranged the initial inspection with the inspection body.

  4. 4
    2022 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

    What we did. We prepared the electrical installation documents and processed its registration.

  5. 5
    2022 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We submitted the notification of opening with the activity's technical documents.

The finished premises

Work area with perforated ceiling and cassette fan coils
Work area with perforated ceiling and cassette fan coils
Reception with a red wall and access to the toilets
Reception with a red wall and access to the toilets