The client wanted to set up their headquarters and their footwear and clothing distribution warehouse in a newly built industrial unit, with offices and as much storage space as possible. We began with a layout study and, based on their requirements, worked with the client on how to make the most of the unit within the safety requirements, and we consulted the fire service beforehand.

We then wrote the activity and fire-protection projects and obtained the fire service's favourable reports. We designed the installations, arranged the electricity supply, managed the electrical installation and coordinated the documents for the others. With the approved collaborating body's favourable certification we submitted the notification of opening of the activity, and we also prepared the self-protection plan.

  • Technical report
  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Building service connection
  • Fire protection
  • Drawings
  • Technical advice
  • Other work

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2019 Barcelona City Council Passed

    Fire-prevention report

    What it is. Report by the fire service on the fire-prevention measures of a project, such as evacuation or fire resistance. Some activities require it because of their size or risk (Catalan Law 3/2010).

    What we did. We prepared the fire-prevention documents and proposed the necessary measures until we obtained the favourable report.

  2. 2
    2021 Government of Catalonia

    Registration of the low-voltage installation

    What it is. Registration of the low-voltage electrical installation with the Government of Catalonia, with the installer's certificate and, where needed, the design and initial inspection. It is essential to contract the power supply.

    What we did. We prepared the electrical installation documents and processed its registration.

  3. 3
    2021 Government of Catalonia

    Registration of the fire-protection installation

    What it is. Registration with the Government of Catalonia of fire-protection installations, such as extinguishers, fire hose reels or automatic detection or suppression systems, with the installer's certificate (RIPCI).

    What we did. We coordinated with the installer the documents for the fire-protection installation and its registration.

  4. 4
    2021 Government of Catalonia

    Registration of the thermal installation

    What it is. Registration with the Government of Catalonia of heating, air-conditioning or hot water installations that require it because of their power, with the installer's certificate and, where required, the design (RITE).

    What we did. We coordinated with the installer the documents for the thermal installation and its registration.

  5. 5
    2022 Approved collaborating body Accepted

    Technical certification by an approved inspection body

    What it is. Review of the project and the finished works by a collaborating body accredited by the authorities, which certifies to the City Council that the activity complies with the rules. Some municipalities require it to open.

    What we did. We dealt with the approved collaborating body's document review and visits until it issued its technical certification.

  6. 6
    2022 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

    What we did. We wrote the activity project and the technical certificate and submitted the notification of opening.

The finished premises

Aisle between shelves of shoe boxes in the warehouse
Aisle between shelves of shoe boxes in the warehouse
Roof with the three outdoor air-conditioning units, the heat-recovery unit and its ducts
Roof with the three outdoor air-conditioning units, the heat-recovery unit and its ducts
Ventilation duct with grilles above the basement shelving