File 481 · 2013 · Barcelona

Espai Capra

Bar and café

procedures
3
authorities
3
year
1

The commission

  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2014 Approved collaborating body

    Technical certification by an approved inspection body

    What it is. Review of the project and the finished works by a collaborating body accredited by the authorities, which certifies to the City Council that the activity complies with the rules. Some municipalities require it to open.

  2. 2
    2014 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

  3. 3
    2014 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.