File 412 · 2012 · Barcelona

Timesburg

Bar and café

procedures
5
authorities
3
years
2

The commission

  • Feasibility study
  • Activity project
  • Prior notification
  • Technical certificate
  • Low-voltage electrical installation
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2012 Barcelona City Council Passed

    Planning report

    What it is. Report by the City Council stating whether a use or activity is compatible with the planning rules at a specific location. It is best requested before committing to the premises or submitting the project.

  2. 2
    2012 Inspection body Passed

    Technical certification by an approved inspection body

    What it is. Review of the project and the finished works by a collaborating body accredited by the authorities, which certifies to the City Council that the activity complies with the rules. Some municipalities require it to open.

  3. 3
    2012 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

  4. 4
    2013 Barcelona City Council

    Prior notification of opening

    What it is. Notice to the City Council, with the technical documents, that a business not requiring a licence is about to open. The council reviews it and may inspect the premises after opening.

  5. 5
    2013 Distribution company

    New electricity supply

    What it is. Request to the distribution company for a new electricity supply point, including a temporary supply for building works. The company sets the technical and financial terms for connecting to its grid.