File 319 · 2010 · Barcelona

Bar Granja La Xurreria

Bar and café

procedures
5
authorities
2
years
2

The commission

  • Activity project
  • Environmental licence
  • Building project
  • Low-voltage electrical installation
  • Technical certificate
  • Terrace licence
  • Thermal installation
  • Technical advice

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2010 Barcelona City Council

    Prior notification of works

    What it is. Notice to the City Council, before starting, of simple works that need no licence, such as interior refurbishments not affecting the structure, signs or solar panels. Depending on the works, technical documents are attached.

  2. 2
    2011 Inspection body Passed

    Initial low-voltage inspection

    What it is. Inspection by an inspection body before commissioning electrical installations that require it because of their power or use, such as premises open to the public. It checks compliance with the REBT.

  3. 3
    2011 Barcelona City Council Granted

    Activity licence

    What it is. Municipal permit authorising an activity in specific premises after its technical project has been reviewed. Some by-laws require it, and it was the usual regime before today's notifications and declarations.

  4. 4
    2011 Barcelona City Council

    Technical certificate of the activity

    What it is. Document signed by the engineer certifying that the premises and their installations have been built as designed and comply with the applicable rules. It is submitted to the City Council in order to open.

  5. 5
    2011 Inspection body Passed

    Sound insulation test

    What it is. On-site test by an accredited body measuring the sound insulation, or the noise reaching neighbouring homes, and checking that it meets the limits of the local by-law and Catalan Law 16/2002.