File 539 · 2014 · Barcelona

Other activities

procedures
2
authority
1
year
1

The commission

  • Building service connection

Procedures

Step by step, from the first visit to the final paperwork.

  1. 1
    2014 Distribution company

    New electricity supply

    What it is. Request to the distribution company for a new electricity supply point, including a temporary supply for building works. The company sets the technical and financial terms for connecting to its grid.

  2. 2
    2014 Distribution company

    Service connection design with the distribution company

    What it is. Design of the service connection or grid extension needed for a supply, which the distribution company reviews and approves before it is built and becomes part of its network.